Construction materials cost 11.5% more than a year ago, according to an Associated Builders and Contractors analysis of federal Producer Price Index data released Nov. 13. Prices held flat in October, but that pause came from cheaper oil and lumber, not from relief on the metals, panels and freight that show up in your repair invoices. If your 2027 operating and capital budgets are still pencilled at last year's cost levels, now is the time to fix them.
What happened
ABC reported that construction input prices were virtually unchanged in October from September, while nonresidential inputs rose 0.2% for the month. Year over year, both overall and nonresidential materials prices are up 11.5%.
The flat month was mostly an energy story. ABC said crude petroleum fell 10.3% in October and unprocessed energy materials fell 7.7%, while natural gas rose 3.7%. ABC chief economist Anirban Basu said iron, steel and copper, materials affected by tariffs, are still "experiencing rapid price escalation," and that nonresidential input prices will likely keep rising in the months ahead.
Bisnow's breakdown of the same data shows multifamily construction inputs were flat month over month, and input costs for maintenance and repairs fell 0.2%, the only segment that declined. Steel mill products rose 2.7% in October.
The residential side looks similar. A National Association of Home Builders analysis, reported by HousingWire, found that inputs to new residential construction rose 10.4% over the past year, against 6.5% for overall final-demand producer prices. Within that index:
| Input | 12-month change |
|---|---|
| Building materials | +5.8% |
| Softwood veneer and plywood | +24.5% |
| Particleboard and fiberboard | +13.9% |
| No. 2 diesel fuel | +115.2% |
| Trade services (dealer and distributor margins) | +13.2% |
| Transportation and warehousing | +24.6% |
Why it matters for property managers
These are producer prices for inputs, not the price a vendor quotes you. Labor, overhead and margin sit on top. But input costs are where bids start, and the pattern matters for operators in three ways.
One flat month is not a trend. October's pause came from energy and lumber. The categories that drive turn and capital costs, such as panels used in cabinets and millwork, metals, and delivered freight, are still climbing. NAHB's numbers show service inputs up 11.3% year over year, and services often adjust more slowly than commodities. A cheaper month for crude oil does not mean your cabinet replacement got cheaper.
Small repairs and big projects are moving differently. Maintenance and repair inputs dipped 0.2% in October. That is a one-month figure, so do not treat it as a discount. Larger work that leans on steel, copper and plywood (roofs, structural repairs, plumbing repipes, electrical upgrades) carries more of the price risk.
Contractor capacity may loosen. ABC's backlog indicator for commercial and industrial contractors fell to 8.1 months in October, down 0.6 months from September, and Bisnow reported backlog is shrinking in nearly every sector except data centers. Shorter backlogs can mean contractors are more willing to compete on price and schedule for work booked now. That is a reason to get bids, not a guarantee of lower quotes.
What to do this week
- Re-run your 2027 repair and maintenance line. If last year's budget assumed low single-digit cost growth, compare it with the 10.4% rise in residential inputs and the 11.5% rise in overall construction inputs. Pick an assumption you can defend to owners and write down where it came from.
- Split capital projects by material exposure. Tag each planned project by its main inputs: metals, panels and plywood, or labor-heavy work. Put a larger contingency on the projects tied to steel and copper, where Basu says rapid price escalation means nonresidential input prices will likely keep rising, and on plywood, which NAHB data shows up 24.5% in a year.
- Ask for price-hold windows on big jobs. For roofs, repipes and any 2027 capital work, ask vendors how long their quote holds and whether materials can be bought now. Compare that with the cost of storing materials and paying early.
- Bid out work while backlogs are shorter. Use the shrinking contractor backlog to get competing quotes on projects you were planning to sole-source.
- Check delivery and freight charges. With transportation and warehousing up 24.6%, look at the delivery, fuel and restocking lines on supplier invoices and ask your main vendors about consolidated deliveries.
- Review lease clauses and owner agreements before passing costs through. How much repair cost you can recover from residents, and how, depends on your leases and on state and local law. Confirm with local counsel before changing fees or charge-backs.
What we're watching
- The next PPI release. Whether metals keep rising while energy falls will shape whether Basu's expectation of further nonresidential increases holds.
- Tariff-affected materials. Iron, steel and copper are the categories ABC singled out. Any change in trade policy would show up in roofing, plumbing and electrical bids first.
- Contractor backlog. If ABC's backlog figure keeps falling, operators should have more leverage on bids in the first half of 2027.
- Services inflation. NAHB's figures show distribution and freight costs rising faster than many materials. That part of the bill is harder to shop away.